APP ID | Queue # | Qualify Date | Process | Status | DER Type and Size | Sub - Fdr - Phs |
---|---|---|---|---|---|---|
APP4582 | 1 | 9/14/2021 12:01:40 PM | Fast Track | DER Installation and Interconnection | Solar PV 23.400 kW | 10 - 4 - A |
APP5368 | 2 | 12/17/2021 3:24:32 PM | Fast Track | Pending Engineer Review | Combined Heat and Power 20.000 kW | 13 - 2 - A |
APP5683 | 3 | 3/4/2022 4:15:31 PM | Simplified | DER Installation and Interconnection | Solar PV 5.220 kW | 6 - 2 - A |
APP5730 | 4 | 5/13/2022 2:26:20 PM | Simplified | DER Installation and Interconnection | Solar PV 11.400 kW | 14 - 4 - A |
APP5994 | 5 | 5/17/2022 1:11:35 PM | Fast Track | DER Installation and Interconnection | Solar PV 24.940 kW | 14 - 3 - B |