APP ID | Queue # | Qualify Date | Process | Status | DER Type and Size | Sub - Fdr - Phs |
---|---|---|---|---|---|---|
APP6791 | 1 | 9/14/2022 8:35:32 AM | Simplified | DER Installation and Interconnection | Solar PV 15.200 kW | 1 - East - AC |
APP6715 | 2 | 9/15/2022 5:07:33 PM | Simplified | DER Installation and Interconnection | Solar PV 11.880 kW | 1 - East - B |
APP6889 | 3 | 9/28/2022 12:16:40 PM | Simplified | DER Installation and Interconnection | Solar PV 5.124 kW | 1 - West - A |
APP7362 | 4 | 2/9/2023 2:00:00 PM | Simplified | DER Installation and Interconnection | Solar PV 8.376 kW | 1 - East - B |
APP7630 | 5 | 3/16/2023 4:26:14 PM | Simplified | DER Installation and Interconnection | Solar PV 7.150 kW | 1 - East - B |
APP4466 | 0 | 4/23/2021 10:01:17 AM | Simplified | Interconnected | Solar PV 5.580 kW | 1 - East - B |
APP4738 | 0 | 6/25/2021 1:04:27 PM | Simplified | Interconnected | Solar PV 6.670 kW | 1 - West - B |
APP4726 | 0 | 6/29/2021 12:32:59 PM | Simplified | Interconnected | Solar PV 7.600 kW | 1 - East - C |