APP ID | Queue # | Qualify Date | Process | Status | DER Type and Size | Sub - Fdr - Phs |
---|---|---|---|---|---|---|
APP3522 | 1 | 12/30/2020 4:08:16 PM | Simplified | DER Installation and Interconnection | Solar PV 1.600 kW | 4 - 3 - A |
APP4822 | 2 | 8/9/2021 1:59:28 PM | Simplified | DER Installation and Interconnection | Solar PV 4.350 kW | 1 - 2 - C |
APP5008 | 3 | 8/31/2021 2:15:39 PM | Simplified | Inspection and Testing | Solar PV 3.480 kW | 3 - 1 - C |
APP5382 | 4 | 12/2/2021 3:33:12 PM | Simplified | DER Installation and Interconnection | Solar PV 19.040 kW | 1 - 2 - C |
APP6189 | 5 | 6/15/2022 3:14:57 PM | Simplified | DER Installation and Interconnection | Solar PV 4.886 kW | 5 - 2 - C |
APP6297 | 6 | 7/6/2022 12:16:21 PM | Simplified | Pending Contract (Utility) | Solar PV 12.564 kW | 2 - 2 - C |
APP6226 | 7 | 7/6/2022 12:37:40 PM | Simplified | DER Installation and Interconnection | Solar PV 9.772 kW | 4 - 1 - B |
APP6242 | 8 | 7/6/2022 1:50:29 PM | Simplified | DER Installation and Interconnection | Solar PV 6.222 kW | 4 - 3 - B |
APP6068 | 9 | 7/9/2022 9:45:55 AM | Fast Track | DER Installation and Interconnection | Solar PV 38.280 kW | 1 - 1 - A |
APP6403 | 10 | 8/3/2022 10:59:03 AM | Simplified | Pending Engineer Review | Solar PV 7.600 kW | 2 - 3 - B |