Current Application Queue

APP ID Queue # Qualify Date Process Status DER Type and Size Sub - Fdr - Phs
APP3936 1 11/25/2020 2:12:47 PM Simplified DER Installation and Interconnection Solar Photovoltaic 13.96 kW 7 - 2 - B
APP3865 2 11/13/2020 3:32:52 PM Simplified DER Installation and Interconnection Solar Photovoltaic 6.00 kW 6 - 3 - A
APP3885 3 11/6/2020 2:52:52 PM Simplified DER Installation and Interconnection Solar Photovoltaic 12.00 kW 4 - 2 - B
APP3802 4 10/22/2020 7:06:25 AM Simplified DER Installation and Interconnection Solar Photovoltaic 12.00 kW 5 - 3 - B
APP3745 5 10/14/2020 8:06:07 AM Simplified Project Complete Solar Photovoltaic 8.20 kW 5 - 2 - B
APP3735 6 10/13/2020 3:21:44 PM Simplified DER Installation and Interconnection Solar Photovoltaic 3.80 kW 3 - 1 - C
APP3560 7 9/15/2020 6:42:07 AM Simplified Project Complete Solar Photovoltaic 7.12 kW 4 - 2 - A
APP3542 8 9/10/2020 3:59:05 PM Simplified Project Complete Solar Photovoltaic 11.71 kW 8 - 3 - A
APP3518 9 9/3/2020 9:43:12 AM Simplified Project Complete Solar Photovoltaic 19.00 kW 1 - 3 - C
APP3395 10 8/3/2020 9:50:59 AM Simplified Inspection and Testing Solar Photovoltaic 4.13 kW 1 - 3 - A
APP3359 11 7/23/2020 10:51:00 AM Simplified Project Complete Solar Photovoltaic 20.00 kW 1 - 3 - B
APP3270 12 6/24/2020 12:07:31 AM Simplified Project Complete Solar Photovoltaic 3.84 kW 1 - 4 - C
APP3160 13 5/22/2020 3:16:21 PM Simplified Project Complete Solar Photovoltaic kW 6 - 3 - A
APP3041 14 4/16/2020 2:19:07 PM Fast Track Inspection and Testing Solar Photovoltaic 39.99 kW 7 - 1 - A
APP2910 15 3/6/2020 10:21:20 AM Simplified Project Complete Solar Photovoltaic 10.00 kW 5 - 3 - C
APP2685 16 12/13/2019 11:30:08 AM Simplified Project Complete Solar Photovoltaic 7.60 kW 1 - 4 - A
APP2588 17 11/11/2019 6:04:43 AM Simplified Project Complete Solar Photovoltaic 12.50 kW 6 - 2 - B
APP2566 18 11/9/2019 9:27:12 AM Simplified Project Complete Solar Photovoltaic 19.00 kW 1 - 4 - B
APP2512 19 10/24/2019 9:27:00 AM Simplified Project Complete Solar Photovoltaic 11.40 kW 2 - 1 - B
APP2416 20 10/7/2019 4:34:47 PM Simplified Project Complete Solar Photovoltaic 12.00 kW 4 - 1 - A
APP2391 21 10/3/2019 12:54:44 PM Simplified Project Complete Solar Photovoltaic 15.00 kW 8 - 1 - A
APP2130 22 9/9/2019 9:23:50 AM Simplified Project Complete Solar Photovoltaic 11.40 kW 8 - 1 - A
APP1975 23 9/5/2019 1:51:43 PM Simplified Project Complete Solar Photovoltaic kW 6 - 2 - C
APP1850 0 9/9/2019 8:35:54 AM Simplified Withdrawn Solar Photovoltaic 3.84 kW 1 - 4 - C
APP4004 0 12/18/2020 11:24:00 AM Simplified Pending Signature Solar Photovoltaic 6.00 kW - -

 

 

  © 2021 - Application developed and maintained by STAR Energy Services LLC