APP ID | Queue # | Qualify Date | Process | Status | DER Type and Size | Sub - Fdr - Phs |
---|---|---|---|---|---|---|
APP6232 | 1 | 7/11/2022 11:00:00 AM | Simplified | DER Installation and Interconnection | Solar PV 7.080 kW | 3 - 5 - B |
APP6549 | 2 | 9/6/2022 4:00:00 PM | Simplified | DER Installation and Interconnection | Solar PV 6.588 kW | 5 - 2 - C |
APP7145 | 3 | 11/10/2022 3:11:29 PM | Fast Track | DER Installation and Interconnection | Solar PV 38.520 kW | 7 - 2 - C |
APP7144 | 4 | 11/10/2022 3:24:23 PM | Fast Track | DER Installation and Interconnection | Solar PV 38.520 kW | 7 - 1 - A |
APP7192 | 5 | 11/18/2022 3:26:26 PM | Simplified | DER Installation and Interconnection | Solar PV 13.500 kW | 5 - 2 - C |
APP6995 | 6 | 12/1/2022 4:15:19 PM | Simplified | DER Installation and Interconnection | Solar PV 6.588 kW | 203 - 3 - A |
APP6517 | 7 | 1/9/2023 3:07:48 PM | Fast Track | Pending Contract (Utility) | Solar PV 23.700 kW | 7 - 3 - B |
APP7381 | 8 | 1/20/2023 8:00:00 AM | Fast Track | DER Installation and Interconnection | Solar PV 26.610 kW | 4 - 1 - B |
APP7002 | 9 | 1/25/2023 1:55:30 PM | Simplified | Pending Contract (Customer) | Solar PV 5.856 kW | 7 - 2 - B |
APP6407 | 0 | 7/19/2022 8:15:21 AM | Fast Track | Interconnected | Solar PV 24.000 kW | 203 - 6 - C |
APP6585 | 0 | 8/25/2022 3:00:00 PM | Simplified | Interconnected | Solar PV 5.856 kW | 203 - 3 - B |
APP6588 | 0 | 9/26/2022 12:52:02 PM | Simplified | Interconnected | Solar PV 8.650 kW | 5 - 2 - A |
APP6595 | 0 | 8/26/2022 9:00:00 AM | Simplified | Interconnected | Solar PV 8.418 kW | 203 - 4 - C |
APP6873 | 0 | 10/3/2022 2:34:44 PM | Simplified | Interconnected | Solar PV 8.000 kW | 7 - 2 - C |
APP6968 | 0 | 10/18/2022 9:40:25 AM | Simplified | Interconnected | Solar PV 7.320 kW | 5 - 1 - C |
APP6964 | 0 | 10/13/2022 7:03:53 PM | Fast Track | Interconnected | Solar PV 18.000 kW | 7 - 2 - C |