APP ID | Queue # | Qualify Date | Process | Status | DER Type and Size | Sub - Fdr - Phs |
---|---|---|---|---|---|---|
APP4015 | 1 | 12/22/2020 11:39:11 AM | Simplified | Facilities Construction | Solar Photovoltaic 11.38 kW | 3 - 5 - A |
APP4015 | 2 | 12/22/2020 11:39:11 AM | Simplified | Facilities Construction | Solar Photovoltaic 11.38 kW | 3 - 5 - A |
APP3054 | 3 | 4/15/2020 11:07:24 AM | Simplified | Facilities Construction | Solar Photovoltaic kW | 3 - 2 - A |
APP2579 | 4 | 11/12/2019 11:14:41 AM | Simplified | DER Installation and Interconnection | Solar Photovoltaic 8.12 kW | 3 - 2 - B |
APP2579 | 5 | 11/12/2019 11:14:41 AM | Simplified | DER Installation and Interconnection | Solar Photovoltaic 8.12 kW | 3 - 2 - B |
APP2258 | 6 | 10/2/2019 5:05:59 PM | Simplified | Project Complete | Solar Photovoltaic 5.00 kW | 7 - 1 - B |
APP2359 | 7 | 10/1/2019 12:43:44 PM | Simplified | Project Complete | Solar Photovoltaic 5.00 kW | 7 - 1 - B |
APP2321 | 8 | 9/25/2019 9:34:07 AM | Simplified | Project Complete | Solar Photovoltaic 5.00 kW | 203 - 6 - C |
APP1543 | 9 | 8/15/2019 12:16:25 PM | Simplified | Project Complete | Solar Photovoltaic 6.96 kW | 7 - 3 - A |
APP1453 | 10 | 7/30/2019 7:42:57 AM | Simplified | Final Accounting | Solar Photovoltaic 0.50 kW | 5 - 4 - C |
APP1119 | 11 | 7/1/2019 7:21:12 PM | Simplified | Project Complete | Solar Photovoltaic 4.80 kW | 5 - 2 - C |
APP1069 | 12 | 6/28/2019 8:48:21 PM | Simplified | Project Complete | Solar Photovoltaic 5.00 kW | 5 - 1 - A |