APP ID | Queue # | Qualify Date | Process | Status | DER Type and Size | Sub - Fdr - Phs |
---|---|---|---|---|---|---|
APP6232 | 1 | 7/11/2022 11:00:00 AM | Simplified | DER Installation and Interconnection | Solar PV 7.080 kW | 3 - 5 - B |
APP6549 | 2 | 9/6/2022 4:00:00 PM | Simplified | DER Installation and Interconnection | Solar PV 6.588 kW | 5 - 2 - C |
APP6517 | 3 | 1/9/2023 3:07:48 PM | Fast Track | DER Installation and Interconnection | Solar PV 23.700 kW | 7 - 3 - B |
APP7381 | 4 | 1/20/2023 8:00:00 AM | Fast Track | DER Installation and Interconnection | Solar PV 26.610 kW | 4 - 1 - B |
APP7598 | 5 | 3/8/2023 3:34:20 PM | Simplified | DER Installation and Interconnection | Solar PV 12.500 kW | 7 - 1 - A |
APP7619 | 6 | 3/24/2023 9:05:07 AM | Simplified | DER Installation and Interconnection | Solar PV 9.150 kW | 7 - 1 - C |
APP7631 | 7 | 4/20/2023 3:00:00 PM | Simplified | DER Installation and Interconnection | Solar PV 9.516 kW | 5 - 3 - C |
APP7575 | 8 | 4/21/2023 9:00:00 AM | Simplified | DER Installation and Interconnection | Solar PV 15.000 kW | 3 - 2 - B |
APP7411 | 9 | 4/21/2023 2:10:51 PM | Simplified | DER Installation and Interconnection | Solar PV 4.026 kW | 5 - 2 - C |
APP7839 | 10 | 5/18/2023 6:20:41 PM | Simplified | Pending Engineer Review | Solar PV 7.320 kW | 203 - 3 - A |
APP6995 | 0 | 12/1/2022 4:15:19 PM | Simplified | Interconnected | Solar PV 6.588 kW | 203 - 3 - A |
APP7002 | 0 | 1/25/2023 1:55:30 PM | Simplified | Interconnected | Solar PV 5.856 kW | 7 - 2 - B |